40 North Main St., Los Altos

In late 2018, a developer in Los Altos took a discretionary project that had been denied by the Los Altos City Council and reworked it to qualify for ministerial approval under SB 35. The project, which had initially been entirely office space was converted to a mixed-use development with multiple on-site below-market-rate units. 

The developer submitted an application for ministerial approval to the Los Altos Planning Department in November of 2018 and in December of 2018 the Planning Department informed the developer that the project did not qualify for ministerial approval under SB 35. They alleged that the project did not comply with parking egress standards and that the project should be subject to a 50% affordability threshold rather than a 10% affordability threshold. The developer disagreed with this assessment and contended that neither of these points rendered the project ineligible for streamlining. In particular the developer pointed out that the city failed to submit the mandatory annual housing production report required by state law automatically setting the SB 35 streamlining threshold at 10%.The Planning Department still maintains that the project violates design standards related to parking but they concede that the 10% threshold is the correct one.

The Planning Department also alleged in their December letter that the project did not qualify for streamlining under SB 35 because less than ⅔ of the project’s sq. footage was residential. This assertion is clearly unfounded and the California Department of Housing and Community Development has issued an advisory letter confirming this. Residential sq. footage for the purposes of SB 35 includes both the floor area of the actual units and the floor area of any residential parking. Under this definition, the project exceeds ⅔ residential floor area and qualifies for streamlining under SB 35.

SB 35 sets forth a 60 day timeline from the submittal of a project application to any denial or approval by an agency. To deny a project under this process it must be found to violate specific objective design or zoning standards and this must be communicated to the project sponsor within 60 days. The initial application for this project was submitted on November 8, 2018 and therefore the 60 day clock elapsed on January 7, 2019. This puts only the first response from the Planning Department within the acceptable timeline. All other communication is invalid, though the project sponsor maintains that the concerns communicated after January 7 were also baseless.

In subsequent communication in January and February of 2019 the Planning Department in Los Altos raised additional concerns regarding the projects utilization of state and local density bonus programs and lack of sufficient parking circulation. The density bonus concern is difficult to adjudicate and rests on differing interpretations of local and state law. The parking circulation assertion is not founded on a specific statutory standard and so cannot be considered to be an objective design standard. Regardless none of these concerns, no matter how baseless, have any bearing on the project as they were brought up after the 60 day window for project denial/approval had elapsed.

 

This case seeks to defend SB 35 from being rendered toothless. The key contention in this case is that a city must communicate all violations of objective standards within 60 days of receiving an application. If the City in this case is relieved of this responsibility it will seriously undermine the “streamlining” aspect of SB 35. Utilizing a streamlined procedure becomes significantly less attractive to developers if the law’s time constraints are unenforceable.

This case is also a test of what can be considered an objective standard for the purposes of ministerial approval or denial. Denials under SB 35 are contingent on the identification of objective standards because the law, and ministerial processes more generally, are meant to eliminate discretion and subjective criteria from planning processes. The Planning Department in Los Altos alleges that they did cite a specific objective standard in their denial of the project. They asserted that the project failed to comply with standards relating to parking ingress and egress. The specific citation however was to a diagram appearing in the City’s building code with specifications for vehicle ramps. The application of this specific portion of building code to this project, which uses a parking lift rather than a ramp, requires far too much extrapolation to be considered objective. The application of unrelated standards to matters of design, especially when the standards have been applied differentially in the past, is fundamentally subjective. A loss on this point would set a bad precedent and imply that planning departments have much more discretion in denying projects than the law sought to provide.

Lastly, it is important that this case upholds the interpretation that residential sq. footage includes residential parking. Many of the ongoing SB35 projects in the Bay Area are mixed use as office or commercial space can help to subsidize the affordable units. If the parking that accompanies residential units is not counted as residential floor space it would become extremely difficult to build mixed-use ministerial projects.

Timeline

  • November 8, 2018 The Developer applied for ministerial approval of the 40 Main St project under SB 35.
  • December 7, 2018 The Planning Department of the City of Los Altos issues its first response to the Developer and deems the project ineligible ministerial approval under SB 35. The City contends that the project does not provide enough affordable housing and that it violates design standards relating to parking.
  • January 7, 2019 The 60 day deadline for response mandated by SB 35 expires.
  • January 10, 2019 Holland and Knight responds to the City of Los Altos in a letter refuting the alleged violations of objective standards identified by the City.
  • February 6, 2019 The Planning Department of the City of Los Altos responds a second time. Identifying new objective standards that the project allegedly violates. 
  • February 19, 2019 Holland and Knight responds again to the City of Los Altos. Once again, they contend that the City has failed to find any violations of objective standards.
  • April 9, 2019 The Los Altos City Council hears the appeal of the Planning Departments denial of the project. The City Council denies the appeal.

Press

Status: Litigation in progress

Filings and Letters

DateKindAuthorTitleSummary
July 22, 2019CaRLASummons

Timeline Press Status: Filings and Letters DateKindAuthorTitleSummary Last […]

July 22, 2019CaRLACivil Case Cover Sheet

Timeline Press Status: Filings and Letters DateKindAuthorTitleSummary Last […]

July 22, 2019CaRLAPetition for Writ

Timeline Press Status: Filings and Letters DateKindAuthorTitleSummary Last […]

Last modified 2019-08-15 03:43